| Budget Group : Earned Value Management Examples | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 4.663 | mile | 3,000,000.00 | 2,331,500.00 | 2,331,500.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 4.663 | mile | 3,000,000.00 | 2,331,500.00 | 2,331,500.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 4663000.00 | 0.00 | 4663000.00 | 4663000.00 |  | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 13.500 | mile | 4,900.00 | 4,725.00 | 4,725.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 6.750 | hour | 455.00 | 438.75 | 438.75 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 20.250 | hour | 1,137,955.00 | 577.60 | 577.60 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 5602.50 | 138.85 | 0.00 | 5741.35 | 5741.35 | 0.00 |  | 
      
        | Budget : EVM 01 Planned Budget | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 4.000 | mile | 2,000,000.00 | 2,000,000.00 | 2,000,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 4.000 | mile | 2,000,000.00 | 2,000,000.00 | 2,000,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 4000000.00 | 0.00 | 4000000.00 | 4000000.00 |  | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 8.000 | mile | 2,800.00 | 2,800.00 | 2,800.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 4.000 | hour | 260.00 | 260.00 | 260.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 12.000 | hour | 650,260.00 | 342.28 | 342.28 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 3320.00 | 82.28 | 0.00 | 3402.28 | 3402.28 | 0.00 |  | 
      
        | Time Period : 2013 Planned Time Period | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 4.000 | mile | 2,000,000.00 | 2,000,000.00 | 2,000,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 4.000 | mile | 2,000,000.00 | 2,000,000.00 | 2,000,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 4000000.00 | 0.00 | 4000000.00 | 4000000.00 |  | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 8.000 | mile | 2,800.00 | 2,800.00 | 2,800.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 4.000 | hour | 260.00 | 260.00 | 260.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 12.000 | hour | 650,260.00 | 342.28 | 342.28 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 3320.00 | 82.28 | 0.00 | 3402.28 | 3402.28 | 0.00 |  | 
      
        | Outcomes | 
      
        | Outcome | 
      
        | 2013, Q1 RR Track Planned | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 1000000.00 | 0.00 | 1000000.00 | 1000000.00 |  | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Output : 2013 RR Track | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Output : 2013 RR Track Site Prep | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Outcome | 
      
        | 2013, Q2 RR Track Planned | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 1000000.00 | 0.00 | 1000000.00 | 1000000.00 |  | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Output : 2013 RR Track | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Output : 2013 RR Track Site Prep | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Outcome | 
      
        | 2013, Q3 RR Track Planned | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 1000000.00 | 0.00 | 1000000.00 | 1000000.00 |  | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Output : 2013 RR Track | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Output : 2013 RR Track Site Prep | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Outcome | 
      
        | 2013, Q4 RR Track Planned | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 1000000.00 | 0.00 | 1000000.00 | 1000000.00 |  | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Output : 2013 RR Track | 
      
        | RR Track Installed | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Output : 2013 RR Track Site Prep | 
      
        | Land | 1.000 | mile | 500,000.00 | 500,000.00 | 500,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 500,000.00 | 0.00 | 500,000.00 | 500,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Operations | 
      
        | Operation | 
      
        | 2013 Rail Road Maintenance, Q1 Planned | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 2.000 | mile | 700.00 | 700.00 | 700.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 3.000 | hour | 162,565.00 | 85.57 | 85.57 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 830.00 | 20.57 | 0.00 | 850.57 | 850.57 | 0.00 |  | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Input : 2013 RR Track Op Bud | 
      
        | Materials | 1.000 | mile | 500.00 | 500.00 | 500.00 | m01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 1.000 | hour | 37,500.00 | 4.84 | 4.84 | e01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 565.00 | 4.84 | 0.00 | 569.84 | 569.84 | 0.00 |  | 
      
        | 1.00 | mile | 569.84 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Input : 2013 RR Track Site Prep Op Bud | 
      
        | Material | 1.000 | mile | 200.00 | 200.00 | 200.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Equipment | 1.000 | hour | 125,000.00 | 15.73 | 15.73 | e01 |  | 
      
        | EVM tutorial example. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 265.00 | 15.73 | 0.00 | 280.73 | 280.73 | 0.00 |  | 
      
        | 1.00 | mile | 280.73 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Operation | 
      
        | 2013 Rail Road Maintenance, Q2 Planned | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 2.000 | mile | 700.00 | 700.00 | 700.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 3.000 | hour | 162,565.00 | 85.57 | 85.57 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 830.00 | 20.57 | 0.00 | 850.57 | 850.57 | 0.00 |  | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Input : 2013 RR Track Op Bud | 
      
        | Materials | 1.000 | mile | 500.00 | 500.00 | 500.00 | m01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 1.000 | hour | 37,500.00 | 4.84 | 4.84 | e01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 565.00 | 4.84 | 0.00 | 569.84 | 569.84 | 0.00 |  | 
      
        | 1.00 | mile | 569.84 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Input : 2013 RR Track Site Prep Op Bud | 
      
        | Material | 1.000 | mile | 200.00 | 200.00 | 200.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Equipment | 1.000 | hour | 125,000.00 | 15.73 | 15.73 | e01 |  | 
      
        | EVM tutorial example. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 265.00 | 15.73 | 0.00 | 280.73 | 280.73 | 0.00 |  | 
      
        | 1.00 | mile | 280.73 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Operation | 
      
        | 2013 Rail Road Maintenance, Q3 Planned | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 2.000 | mile | 700.00 | 700.00 | 700.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 3.000 | hour | 162,565.00 | 85.57 | 85.57 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 830.00 | 20.57 | 0.00 | 850.57 | 850.57 | 0.00 |  | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Input : 2013 RR Track Op Bud | 
      
        | Materials | 1.000 | mile | 500.00 | 500.00 | 500.00 | m01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 1.000 | hour | 37,500.00 | 4.84 | 4.84 | e01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 565.00 | 4.84 | 0.00 | 569.84 | 569.84 | 0.00 |  | 
      
        | 1.00 | mile | 569.84 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Input : 2013 RR Track Site Prep Op Bud | 
      
        | Material | 1.000 | mile | 200.00 | 200.00 | 200.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Equipment | 1.000 | hour | 125,000.00 | 15.73 | 15.73 | e01 |  | 
      
        | EVM tutorial example. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 265.00 | 15.73 | 0.00 | 280.73 | 280.73 | 0.00 |  | 
      
        | 1.00 | mile | 280.73 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Operation | 
      
        | 2013 Rail Road Maintenance, Q4 Planned | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 2.000 | mile | 700.00 | 700.00 | 700.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 3.000 | hour | 162,565.00 | 85.57 | 85.57 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 830.00 | 20.57 | 0.00 | 850.57 | 850.57 | 0.00 |  | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Input : 2013 RR Track Op Bud | 
      
        | Materials | 1.000 | mile | 500.00 | 500.00 | 500.00 | m01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 1.000 | hour | 37,500.00 | 4.84 | 4.84 | e01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 565.00 | 4.84 | 0.00 | 569.84 | 569.84 | 0.00 |  | 
      
        | 1.00 | mile | 569.84 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Input : 2013 RR Track Site Prep Op Bud | 
      
        | Material | 1.000 | mile | 200.00 | 200.00 | 200.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.000 | hour | 65.00 | 65.00 | 65.00 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Equipment | 1.000 | hour | 125,000.00 | 15.73 | 15.73 | e01 |  | 
      
        | EVM tutorial example. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 265.00 | 15.73 | 0.00 | 280.73 | 280.73 | 0.00 |  | 
      
        | 1.00 | mile | 280.73 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Budget : EVM 02 Actual Budget | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 0.663 | mile | 1,000,000.00 | 331,500.00 | 331,500.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 0.663 | mile | 1,000,000.00 | 331,500.00 | 331,500.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 663000.00 | 0.00 | 663000.00 | 663000.00 |  | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 5.500 | mile | 2,100.00 | 1,925.00 | 1,925.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 2.750 | hour | 195.00 | 178.75 | 178.75 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 8.250 | hour | 487,695.00 | 235.32 | 235.32 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 2282.50 | 56.57 | 0.00 | 2339.07 | 2339.07 | 0.00 |  | 
      
        | Time Period : 2013 Actual Time Period | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 0.663 | mile | 1,000,000.00 | 331,500.00 | 331,500.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 0.663 | mile | 1,000,000.00 | 331,500.00 | 331,500.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 663000.00 | 0.00 | 663000.00 | 663000.00 |  | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 5.500 | mile | 2,100.00 | 1,925.00 | 1,925.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 2.750 | hour | 195.00 | 178.75 | 178.75 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 8.250 | hour | 487,695.00 | 235.32 | 235.32 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 2282.50 | 56.57 | 0.00 | 2339.07 | 2339.07 | 0.00 |  | 
      
        | Outcomes | 
      
        | Outcome | 
      
        | 2013, Q1 RR Track Actual | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 0.330 | mile | 500,000.00 | 165,000.00 | 165,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 0.330 | mile | 500,000.00 | 165,000.00 | 165,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 330000.00 | 0.00 | 330000.00 | 330000.00 |  | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Output : 2013 RR Track | 
      
        | RR Track Installed | 0.330 | mile | 500,000.00 | 165,000.00 | 165,000.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 165,000.00 | 0.00 | 165,000.00 | 165,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Output : 2013 RR Track Site Prep | 
      
        | Land | 0.330 | mile | 500,000.00 | 165,000.00 | 165,000.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 165,000.00 | 0.00 | 165,000.00 | 165,000.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Outcome | 
      
        | 2013, Q2 RR Track Actual | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | RR Track Installed | 0.333 | mile | 500,000.00 | 166,500.00 | 166,500.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Land | 0.333 | mile | 500,000.00 | 166,500.00 | 166,500.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 333000.00 | 0.00 | 333000.00 | 333000.00 |  | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Output : 2013 RR Track | 
      
        | RR Track Installed | 0.333 | mile | 500,000.00 | 166,500.00 | 166,500.00 | EVM1 |  | 
      
        | This measures the unit value of 1 mile of installed railroad track. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 166,500.00 | 0.00 | 166,500.00 | 166,500.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Output : 2013 RR Track Site Prep | 
      
        | Land | 0.333 | mile | 500,000.00 | 166,500.00 | 166,500.00 | re01 |  | 
      
        | This subbenefit values the land purchased for a railroad. | 
      
        | Unit Amount | Unit | Total Revenue | Total EAA | Total LCB | Total Unit Benefit | Service Life | P/C Years | Yrs From Base Date | Target Type / AlternType | 
      
        | 1.00 | mile | 166,500.00 | 0.00 | 166,500.00 | 166,500.00 | 0.00 | 0.00 | 0.00 | A; benchmark | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Outcome | 
      
        | 2013, Q3 RR Track Actual | 
      
        | Benefits | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Totals | --- | Total Revenue | Total EAA | Total LCB | Total Unit Benefit |  |  |  |  | 
      
        | Totals | --- | 0.00 | 0.00 | 0.00 | 0.00 |  | 
      
        | SubBenefit Name | SubBenefit Amount | SubBenefit Unit | SubBenefit Price | SubBenefit Total | SubBenefit Unit Total | SubBenefit Label |  | 
      
        | Operations | 
      
        | Operation | 
      
        | 2013 Rail Road Maintenance, Q1 Actual | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 3.000 | mile | 700.00 | 1,050.00 | 1,050.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.500 | hour | 65.00 | 97.50 | 97.50 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 4.500 | hour | 162,565.00 | 128.36 | 128.36 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 1245.00 | 30.86 | 0.00 | 1275.86 | 1275.86 | 0.00 |  | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Input : 2013 RR Track Op Bud | 
      
        | Materials | 1.500 | mile | 500.00 | 750.00 | 750.00 | m01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Labor | 1.500 | hour | 65.00 | 97.50 | 97.50 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 1.500 | hour | 37,500.00 | 7.26 | 7.26 | e01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 847.50 | 7.26 | 0.00 | 854.76 | 854.76 | 0.00 |  | 
      
        | 1.00 | mile | 854.76 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Input : 2013 RR Track Site Prep Op Bud | 
      
        | Material | 1.500 | mile | 200.00 | 300.00 | 300.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 1.500 | hour | 65.00 | 97.50 | 97.50 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Equipment | 1.500 | hour | 125,000.00 | 23.60 | 23.60 | e01 |  | 
      
        | EVM tutorial example. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 397.50 | 23.60 | 0.00 | 421.10 | 421.10 | 0.00 |  | 
      
        | 1.00 | mile | 421.10 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Operation | 
      
        | 2013 Rail Road Maintenance, Q2 Actual | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 1.500 | mile | 700.00 | 525.00 | 525.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 0.750 | hour | 65.00 | 48.75 | 48.75 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 2.250 | hour | 162,565.00 | 64.18 | 64.18 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 622.50 | 15.43 | 0.00 | 637.93 | 637.93 | 0.00 |  | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Input : 2013 RR Track Op Bud | 
      
        | Materials | 0.750 | mile | 500.00 | 375.00 | 375.00 | m01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Labor | 0.750 | hour | 65.00 | 48.75 | 48.75 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 0.750 | hour | 37,500.00 | 3.63 | 3.63 | e01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 423.75 | 3.63 | 0.00 | 427.38 | 427.38 | 0.00 |  | 
      
        | 1.00 | mile | 427.38 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Input : 2013 RR Track Site Prep Op Bud | 
      
        | Material | 0.750 | mile | 200.00 | 150.00 | 150.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 0.750 | hour | 65.00 | 48.75 | 48.75 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Equipment | 0.750 | hour | 125,000.00 | 11.80 | 11.80 | e01 |  | 
      
        | EVM tutorial example. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 198.75 | 11.80 | 0.00 | 210.55 | 210.55 | 0.00 |  | 
      
        | 1.00 | mile | 210.55 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Operation | 
      
        | 2013 Rail Road Maintenance, Q3 Actual | 
      
        | Costs | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Material | 1.000 | mile | 700.00 | 350.00 | 350.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 0.500 | hour | 65.00 | 32.50 | 32.50 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 1.500 | hour | 162,565.00 | 42.79 | 42.79 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Totals | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Totals | 415.00 | 10.29 | 0.00 | 425.29 | 425.29 | 0.00 |  | 
      
        | SubCost Name | SubCost Amount | SubCost Unit | SubCost Price | SubCost Total | SubCost Unit Total | SubCost Label |  | 
      
        | Input : 2013 RR Track Op Bud | 
      
        | Materials | 0.500 | mile | 500.00 | 250.00 | 250.00 | m01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Labor | 0.500 | hour | 65.00 | 32.50 | 32.50 | l01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        | Equipment | 0.500 | hour | 37,500.00 | 2.42 | 2.42 | e01 |  | 
      
        | Sample subcost used in an EVM analysis. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 282.50 | 2.42 | 0.00 | 284.92 | 284.92 | 0.00 |  | 
      
        | 1.00 | mile | 284.92 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a | 
      
        | Input : 2013 RR Track Site Prep Op Bud | 
      
        | Material | 0.500 | mile | 200.00 | 100.00 | 100.00 | m01 |  | 
      
        | EVM tutorial example. | 
      
        | Labor | 0.500 | hour | 65.00 | 32.50 | 32.50 | e01 |  | 
      
        | EVM tutorial example. | 
      
        | Equipment | 0.500 | hour | 125,000.00 | 7.87 | 7.87 | e01 |  | 
      
        | EVM tutorial example. | 
      
        |  | Total OC | Total AOH | Total CAP | Total LCC | Total Unit | Total EAA |  | 
      
        | Unit Amount | Unit | Total Unit Cost | Service Life | P/C Years | Yrs From Base Date | Altern Type | Target Type |  |  | 
      
        | Totals | 132.50 | 7.87 | 0.00 | 140.37 | 140.37 | 0.00 |  | 
      
        | 1.00 | mile | 140.37 | 0.00 | 0.00 | 0.00 | A | benchmark |  |  | 
      
        | Description : Sample analysis used in a DevTreks tutorial. v196a |